St. Armands Resiliency and Flood Mitigation
Funds will support flood-mitigation improvements to address chronic tidal flooding and storm surge impacts in St. Armands Key, with a focus on strengthening stormwater infrastructure and maintaining evacuation access.
Sarasota County
Date Selected: Dec. 16, 2025
Amount Funded: $13,500,000
Agreement Status: Pending
Project Milestones
✅ Step 1: Project Selected by Sarasota County Commission
Step 2: [Pending] HUD Environmental Review Process
Step 3: [Pending] Authority to use grant funds received from HUD
Step 4: [Pending] Construction / Implementation
Step 5: [Pending] Project Complete

St Armands lift station, April 23, 2026